Analysis of the behaviour of stage II cofferdam of TGP
Lots of research work including the site investigation, sampling and testing of the cofferdam and its cut-off walls had been done during the period for the removal of stage II cofferdam of TGP. Some key factors are analyzed and discussed based on these results.