GU Longsheng, ZHANG Yuting. Application of high-strain testing in large-diameter steel pipe pile project in Rudong sea area[J]. Chinese Journal of Geotechnical Engineering, 2024, 46(S1): 138-142. DOI: 10.11779/CJGE2024S10010
Citation: GU Longsheng, ZHANG Yuting. Application of high-strain testing in large-diameter steel pipe pile project in Rudong sea area[J]. Chinese Journal of Geotechnical Engineering, 2024, 46(S1): 138-142. DOI: 10.11779/CJGE2024S10010

Application of high-strain testing in large-diameter steel pipe pile project in Rudong sea area

More Information
  • Received Date: April 30, 2024
  • Based on the initial and repeated high-strain test data of three large-diameter open steel pipe piles in Rudong sea area of Jiangsu Province, a pile end reduction coefficient η applicable to the sea area and the formula for calculating the recovery of bearing capacity is proposed, and a technical basis for evaluating the bearing capacity of large-diameter steel pipe piles in the sea area is provided. According to the high-strain test data of open steel pipe piles, the recovery coefficients of the lateral resistance of the test piles are much greater than those of the end resistance, and the lateral resistance of the piles increases significantly over time, but the increase in the end resistance is very small. Based on this, it is recommended to use the pile end resistance reduction coefficient η= 0.05 for large-diameter open steel pipe piles in the Rudong sea area. In addition, by exploring the recovery and growth mechanism of pile foundation soil, a formula for calculating the recovery of pile foundation bearing capacity is proposed, and the verification error is within 10%.
  • [1]
    LIU R, ZHOU L, LIAN J J, et al. Behavior of monopile foundations for offshore wind farms in sand[J]. Journal of Waterway Port Coastal and Ocean Engineering, 2015, 142(1): 04051010.
    [2]
    码头结构设计规范: JTS 167—2018[S]. 北京: 人民交通出版社, 2018.

    Wharf Structure Design Code: JTS 167—2018[S]. Beijing: China Communications Press, 2018. (in Chinese)
    [3]
    API RP 2A-WSD. Recommended Practice for Planning, Designing, and Constructing Fixed Offshore Platforms- Working Stress Design[S]. API Recommended Practice 2A-WSD, 2010.
    [4]
    倪敏. 大直径钢管桩竖向承载能力研究[D]. 天津: 天津大学, 2014.

    NI Min. Research on Axial Load-Bearing Capacity of Large Diameter Pipe Piles[D]. Tianjin: Tianjin University, 2014. (in Chinese)
    [5]
    刘润, 闫玥, 闫澍旺. 大直径超长桩后继打桩拒锤现象分析及单桩承载力计算[J]. 岩土力学与工程学报, 2008, 27(增刊2): 3459-3464. https://www.cnki.com.cn/Article/CJFDTOTAL-YSLX2008S2027.htm

    LIU Run, YAN Yue, YAN Shuwang. Study on refusal of restarting of large diameter and deep penetration pile and bearing capacity calculation[J]. Chinese Journal of Rock Mechanics and Engineering, 2008, 27(S2): 3459-3464. (in Chinese) https://www.cnki.com.cn/Article/CJFDTOTAL-YSLX2008S2027.htm
    [6]
    李飒, 李婷婷, 张树德, 等. 基于实测数据的桩基承载力恢复计算与分析[J]. 工程力学, 2018, 35(6): 182-190. https://www.cnki.com.cn/Article/CJFDTOTAL-GCLX201806023.htm

    LI Sa, LI Tingting, ZHANG Shude. A study on pile setup based on measured in situ data[J]. Engineering Mechanics, 2018, 35(6): 182-190. (in Chinese)). https://www.cnki.com.cn/Article/CJFDTOTAL-GCLX201806023.htm
    [7]
    杨生彬, 李友东. PHC管桩挤土效应试验研究[J]. 岩土工程技术, 2006, 20(3): 117-120. https://www.cnki.com.cn/Article/CJFDTOTAL-YTGJ200603002.htm

    YANG Shengbin, LI Youdong. Experimental research on compacting effects of PHC piles[J]. Geotechnical Engineering Technique, 2006, 20(3): 117-120. (in Chinese) https://www.cnki.com.cn/Article/CJFDTOTAL-YTGJ200603002.htm
    [8]
    水运工程基桩试验检测技术规范: JTS 240—2020[S]. 北京: 人民交通出版社, 2020.

    Technical Code for Testing and Inspection of Waterway Engineering Foundation Piles: JTS 240—2020[S]. Beijing: China Communications Press, 2020. (in Chinese)
    [9]
    曹宇春, 吴世明, 高广远. 桩基动力检测技术的现状及存在的问题[J]. 上海地质, 2002(81): 43-45. https://www.cnki.com.cn/Article/CJFDTOTAL-SHAD200201015.htm

    CAO Yuchun, WU Shiming, GAO Guangyuan. Application situation of pile dynamic detections and existed problems[J]. Shanhai Geology, 2002(81): 43-45. (in Chinese) https://www.cnki.com.cn/Article/CJFDTOTAL-SHAD200201015.htm
    [10]
    建筑基桩检测技术规范: JGJ 106—2014[S]. 北京: 中国建筑工业出版社, 2014.

    Technical Code for Testing of Building Foundation Piles: JGJ 106—2014[S]. Beijing: China Architecture and Building Press, 2014. (in Chinese)
    [11]
    梁超, 刘润. 大直径钢管桩竖向承载力计算方法研究[J]. 地下空间与工程学报, 2018, 14(1): 169-175. https://www.cnki.com.cn/Article/CJFDTOTAL-BASE201801024.htm

    LIANG Chao, LIU Run. Research on evaluation methods of vertical bearing capacity for large diameter steel pipe pile[J]. Chinese Journal of Underground Space and Engineering, 2018, 14(1): 169-175. (in Chinese) https://www.cnki.com.cn/Article/CJFDTOTAL-BASE201801024.htm
    [12]
    SVINKIN M R. Discussion on setup and relaxation in glacial sand[J]. Journal of Geotechnical Engineering, 1996, 122(4): 319-321.
    [13]
    LONG J, KERRIGAN J, WYSOCKEY M. Measured time effects for axial capacity of driven piling[J]. Transportation Research Record Journal of the Transportation Research Board, 1999, 1663(1): 8-15.