• 全国中文核心期刊
  • 中国科技核心期刊
  • 美国工程索引(EI)收录期刊
  • Scopus数据库收录期刊
李协生. 渔子溪一级水电站地下厂房工程地质问题的处理[J]. 岩土工程学报, 1982, 4(2): 107-118.
引用本文: 李协生. 渔子溪一级水电站地下厂房工程地质问题的处理[J]. 岩土工程学报, 1982, 4(2): 107-118.
Li Xiesheng. Treatment of the Engineering Geologic Problems in the Underground Hydroelectric Power Plant of the Fishermans' Creek Ⅰ[J]. Chinese Journal of Geotechnical Engineering, 1982, 4(2): 107-118.
Citation: Li Xiesheng. Treatment of the Engineering Geologic Problems in the Underground Hydroelectric Power Plant of the Fishermans' Creek Ⅰ[J]. Chinese Journal of Geotechnical Engineering, 1982, 4(2): 107-118.

渔子溪一级水电站地下厂房工程地质问题的处理

Treatment of the Engineering Geologic Problems in the Underground Hydroelectric Power Plant of the Fishermans' Creek Ⅰ

  • 摘要: 本电站地下厂房的地质条件比较复杂。在区域地质构造影响下,陡倾角和缓倾角断裂及其同方向裂隙发育,纵横切割,将厂房和尾水调压井间的岩柱分割成十多个块体,破坏了岩柱的完整性,威胁着岩柱的稳定性。同时,在厂房上下游边墙的局部地段形成比较严重的不稳定岩体。此外,由于地质勘探资料不足,厂房轴线选择和地下建筑物布置也不尽合理,洞室密度过大,交叉口多达19个,这更增加了地下厂房枢纽修建的困难。对比,在各关键部位采取了工程结构处理措施,诸如深孔锚桩、空心锚洞和横向撑墙及撑梁等;调整了局部的布置;采用了比较切合实际的施工程序和一系列施工安全技术措施,如戴、锁、锚、插、撑、箍等。从原型观测和用有限元法对围岩应力应变计算成果的分析看,以上这些措施都是切实有效的,保证了地下厂房的顺利建成和安全运行。今后,仍将继续加强原型观测和研究工作。

     

    Abstract: The geological conditions of this underground hydroelectric power plant is very com- plex. The high angle faults, low angle faults and fractures in the same directions have developed under the influence of areal geological structures. The stability and perfection of the rock pillar between the main machine hall and the tailwater surge chamber was spoiled by longitudinal and transversal fractures which intersected each other and dissected the rock pillar into more than ten rock blocks. Simultaneously, some rather instable rock masses were formed in some parts of the upstream and downstream side-walls of the main machine hall. Besides, in consequence of the insufficiency of geological data and rock test results, the choice of the axis of the main machine hall and the layout of underground structures are not quite ideal. The density of rock chambers is very big, and the intersections of the chambers with lateral galleries totalled nineteen, thus enhanced the difficulty of construction of the underground power plant, Therefore, some suitable engineering structural measures were adopted at the principal positions, such as: the use of deep rock anchor piles, hollow anchor rock chambers, lateral buttress and propped beams; rectification of local layout; the adoption of a more reasonable construction schedule, and a series of constructional safety measures, such as, capping, locking, anchoring, thrusting, bracing, hooping etc. From prototype observations and the results of finite element analysis of the stress and deformation calculation of the surrounding rock1, it is evident that these measures are effective and ensured the completion and safety operation of underground power plant. Further prototype observations and investigations are still under way.

     

/

返回文章
返回