• 全国中文核心期刊
  • 中国科技核心期刊
  • 美国工程索引(EI)收录期刊
  • Scopus数据库收录期刊
施成华, 雷明锋, 彭立敏, 杨伟超, 丁祖德. 隧道底部结构受力与变形的现场测试与分析[J]. 岩土工程学报, 2012, 34(5): 879-884.
引用本文: 施成华, 雷明锋, 彭立敏, 杨伟超, 丁祖德. 隧道底部结构受力与变形的现场测试与分析[J]. 岩土工程学报, 2012, 34(5): 879-884.
SHI Cheng-hua, LEI Ming-feng, PENG Li-min, YANG Wei-chao, DING Zu-de. In-situ monitoring and analysis of mechanical characteristics and deformation of bottom structure of tunnels[J]. Chinese Journal of Geotechnical Engineering, 2012, 34(5): 879-884.
Citation: SHI Cheng-hua, LEI Ming-feng, PENG Li-min, YANG Wei-chao, DING Zu-de. In-situ monitoring and analysis of mechanical characteristics and deformation of bottom structure of tunnels[J]. Chinese Journal of Geotechnical Engineering, 2012, 34(5): 879-884.

隧道底部结构受力与变形的现场测试与分析

In-situ monitoring and analysis of mechanical characteristics and deformation of bottom structure of tunnels

  • 摘要: 采用现场测试方法,对隧道底部结构的变形、仰拱混凝土和钢筋中的应力进行了长期测试和分析。受围岩释放荷载、隧道二衬自重及上部围岩荷载以及道床设施和运营列车荷载的作用,隧道底部结构在整个施工过程中经历了隆起—下沉—隆起—下沉的反复变化过程,仰拱混凝土及钢筋同样经历了拉—压—拉—压的反复变化过程;围岩条件越好,隧道底部结构中的应力和变形最终值及其变化幅值越小;整个隧道施工过程中,隧道底部结构的最大下沉小于 5.0 mm ,混凝土中的最大拉压应力小于 2.0 MPa ,满足高速列车的安全运营要求;隧道二次衬砌施作之前仰拱处于最不利的受力状态,施工中应及时将隧道二衬闭合成环,以保证隧道仰拱结构处于较佳的受力状态;隧道开挖后的应力重分布持续时间一般在 2 a 以上。

     

    Abstract: By means of the in-situ monitoring method, the deformation of bottom structure of tunnel and the stress of concrete and rebars in its inverted arch are tested and analyzed. Under the action of unloading of surrounding rock, the loads of tunnel linings, and the upper surrounding rock auxiliary facilities and train load, the bottom structure of the tunnel witnesses a repeated process of uplift-subsidence-uplift-subsidence during the whole course of tunnel construction, and the concrete and rebars in the inverted arch have a process of tension-compression-tension-compression as well. The better the condition of the surrounding rock, the smaller the values of the deformation and stress and their change ranges. During the whole course of tunnel construction, the maximum subsidence of the bottom structure of the tunnel is less than 5.0 mm, and the maximum tensile and compression stresses are both less than 2.0 MPa, thus high-speed trains can run safely. The inverted arch of the tunnel is in the worst conditions before the tunnel linings are constructed. So the tunnel linings must be constructed in time to make sure that the inverted arch is under better conditions. The redistribution time of the stress on the surrounding rock after tunnel excavation is generally more than two years.

     

/

返回文章
返回