刘金波, 张中南, 孙明, 李冰. 某桩基承载力不满足要求处理实例及分析[J]. 岩土工程学报, 2011, 33(sup2): 58-63.
引用本文: 刘金波, 张中南, 孙明, 李冰. 某桩基承载力不满足要求处理实例及分析[J]. 岩土工程学报, 2011, 33(sup2): 58-63.
LIU Jin - bo, ZH ANG Zho ng- nan, S U N M ing, LI Bing. Treatment and analy sis of pile foundation without satisfying requirements of bearing capacity[J]. Chinese Journal of Geotechnical Engineering, 2011, 33(sup2): 58-63.
Citation: LIU Jin - bo, ZH ANG Zho ng- nan, S U N M ing, LI Bing. Treatment and analy sis of pile foundation without satisfying requirements of bearing capacity[J]. Chinese Journal of Geotechnical Engineering, 2011, 33(sup2): 58-63.

某桩基承载力不满足要求处理实例及分析

Treatment and analy sis of pile foundation without satisfying requirements of bearing capacity

  • 摘要: 通过山东某工程灌注桩承载力不满足要求的成功处理实例,介绍了当桩承载力不满足要求时的处理步骤、分析方法、注意事项。对需要补桩的工程,给出了确定补桩位置、桩长和桩数量的原则。对于补桩位置,应考虑对基础沉降的影响,需结合结构形式、荷载分布特点、地质条件等确定补桩位置,使基础沉降尽可能均匀。对于补桩桩长,应根据桩间距和沉降要求确定,当补桩和原设计桩间距满足规范要求且预估基础沉降满足要求时,可同原桩长;当补桩和原设计桩间距不满足规范要求或预估基础沉降不满足要求时,应考虑桩的相互影响和控制沉降要求,补桩的桩长大于原设计桩长。对于补桩数量,在满足承载力和变形要求的情况下,可采用后注浆等措施提高桩的承载力,减小桩的数量。

     

    Abstract: The handling steps, analytical methods and announcements are introduced by means of a successful treatment example of bored concrete piles without satisfying the requirements of bearing capacity in a project of Shandong. The principles to determine the position of supplement pile , pile length and pile quantity are provided. With regard to the position of the supplement pile, the effect on the foundation settlement , structural form, load distribution , geological conditions and so on should be considered in order to make foundation settlement as uniform as possible. The length of supplement pile should be determined by pile spacing and settlement requirements. When the spacing s of the supplement pile and the original pile satisfy the code and foundation settlement requirements, the supplement pile can be as long as the original pile; when they do not satisfy the code or foundation settlement requirements, the length of the supplement pile should be greater than that of the original pile. Under the condition that the bearing capacity and the deformation requirements are satisfied, the measures such as post-grouting bored concrete piles can be adopted in order to enhance the bearing capacity of the pile and reduce pile quantity as possible.

     

/