盾构工作井围护结构在施工全过程的内力测试分析
Test on the internal forces of the shield work well during construction
-
摘要: 探讨了地铁车站端头井围护结构计算方法 ,结合某地铁车站施工中对盾构工作井端墙的内力现场测试 ,表明连续墙在坑外土体搅拌加固时 ,内力变化最大 ,其次是在基坑开挖阶段 ;内衬墙修好后 ,盾构洞的开凿和盾构的进出洞 ,对连续墙内力的影响较小Abstract: The calculating method of retaining wall in shield work well of metro station is discussed. The internal forces of the wall are observed in a station of Shanghai Metro Line-2. When the soil is treated by the deep mixing method, the maximum internal force variation occurs,and a relatively smaller variation occurs during the excavation of foundation pit. When the lining wall was built, the internal forces change little during the cut of shield cave and the transportation of shield machine into or out of the well.