付艳斌, 王福道, 陆岸典, 张小龙, 洪成雨, 肖惠. 断层破碎带海底盾构隧道管片纵向沉降解析解及应用[J]. 岩土工程学报, 2023, 45(7): 1393-1401. DOI: 10.11779/CJGE20220507
引用本文: 付艳斌, 王福道, 陆岸典, 张小龙, 洪成雨, 肖惠. 断层破碎带海底盾构隧道管片纵向沉降解析解及应用[J]. 岩土工程学报, 2023, 45(7): 1393-1401. DOI: 10.11779/CJGE20220507
FU Yanbin, WANG Fudao, LU Andian, ZHANG Xiaolong, HONG Chengyu, XIAO Hui. Analytical solution to longitudinal settlement of segments of subsea shield tunnels in fault fracture zones and its application[J]. Chinese Journal of Geotechnical Engineering, 2023, 45(7): 1393-1401. DOI: 10.11779/CJGE20220507
Citation: FU Yanbin, WANG Fudao, LU Andian, ZHANG Xiaolong, HONG Chengyu, XIAO Hui. Analytical solution to longitudinal settlement of segments of subsea shield tunnels in fault fracture zones and its application[J]. Chinese Journal of Geotechnical Engineering, 2023, 45(7): 1393-1401. DOI: 10.11779/CJGE20220507

断层破碎带海底盾构隧道管片纵向沉降解析解及应用

Analytical solution to longitudinal settlement of segments of subsea shield tunnels in fault fracture zones and its application

  • 摘要: 断层破碎带地层隧道沉降控制是海底盾构隧道建设的关键问题之一,隧道的不均匀沉降诱发管片环缝张开、错台、螺栓应力增大乃至接缝渗漏水等现象,严重影响隧道结构稳定和运营安全。针对断层破碎带地层海底盾构隧道纵向沉降问题,分析隧道穿越断层破碎带地层全过程,提出了归一化上覆荷载理论公式。通过泰勒级数公式将复杂上覆荷载在5%误差内简化为多段三次多项式函数,结合Timoshenko梁理论推导建立了海底盾构隧道管片纵向沉降及内力系列解析解。最后结合工程实例对理论模型进行了验证。研究表明:断层破碎带内隧道的沉降曲线表现为激增段、缓增段和骤减段。断层破碎带倾角越大,断层破碎带与正常围岩界面附近不均匀沉降越大,断层破碎带对延伸侧1倍破碎带宽度范围内隧道的沉降影响较大;随着断层破碎带宽度的增加,断层破碎带范围内隧道的沉降峰值逐渐增大并趋于稳定,当断层破碎带宽度超过6倍洞径时,隧道的沉降峰值基本保持不变。研究结果可为断层破碎带海底盾构隧道纵向沉降计算和性能评估提供依据。

     

    Abstract: The settlement control of tunnels in fault fracture zones is one of the key problems in the construction of subsea shield tunnels. The differential settlement of the tunnels induces the opening and dislocation of circumferential segment joint, increase of bolt stress and even leakage, which seriously affect the stability of tunnel structure and operation safety. Aiming at the longitudinal settlement of the subsea shield tunnels in the fault fracture zone stratum, through the analysis of the whole process of the tunnels crossing the fault fracture zone stratum, the theoretical formula for the normalized overlying loads is proposed, and the Taylor series expansion method is used to simplify the complex overburden loads into a multi-segment cubic polynomial function within 5% error. Combined with the Timoshenko beam theory, the analytical solution of the longitudinal settlement and internal force of the subsea shield tunnel segments is derived. Finally, the theoretical model is verified by an engineering example. The research shows that the settlement curve of the tunnel in the fault fracture zone shows surge section, slow increase section and sudden decrease section. The greater the dip angle of the fault fracture zone, the greater the differential settlement near the interface between the fault fracture zone and the normal surrounding rock. The fault fracture zone has a great influence on the settlement of the tunnels within the width of one time the fracture zone at the extension side. With the increase of the width of the fault fracture zone, the peak settlement of the tunnel in the fault fracture zone gradually increases and tends to be stable. When the width of the fault fracture zone exceeds 6 times the tunnel diameter, the peak settlement of the tunnel basically remains unchanged. The research results may provide a basis for the longitudinal settlement calculation and performance evaluation of subsea shield tunnels in fault fracture zones.

     

/