曾锃, 赵树祥, 葛龙进, 潘卫平, 李敏, 殷国峰. 罗闸河二级水电站拱坝右岸边坡变形破坏机制研究及治理后评估[J]. 岩土工程学报, 2021, 43(S1): 171-175. DOI: 10.11779/CJGE2021S1031
引用本文: 曾锃, 赵树祥, 葛龙进, 潘卫平, 李敏, 殷国峰. 罗闸河二级水电站拱坝右岸边坡变形破坏机制研究及治理后评估[J]. 岩土工程学报, 2021, 43(S1): 171-175. DOI: 10.11779/CJGE2021S1031
ZENG Zeng, ZHAO Shu-xiang, Ge Long-jin, PAN Wei-ping, LI Min, YIN Guo-feng. Failure mechanism of deformation and evaluation of treatment effect of high slope at right bank of Luozha RiverⅡHydropower Station[J]. Chinese Journal of Geotechnical Engineering, 2021, 43(S1): 171-175. DOI: 10.11779/CJGE2021S1031
Citation: ZENG Zeng, ZHAO Shu-xiang, Ge Long-jin, PAN Wei-ping, LI Min, YIN Guo-feng. Failure mechanism of deformation and evaluation of treatment effect of high slope at right bank of Luozha RiverⅡHydropower Station[J]. Chinese Journal of Geotechnical Engineering, 2021, 43(S1): 171-175. DOI: 10.11779/CJGE2021S1031

罗闸河二级水电站拱坝右岸边坡变形破坏机制研究及治理后评估

Failure mechanism of deformation and evaluation of treatment effect of high slope at right bank of Luozha RiverⅡHydropower Station

  • 摘要: 2013年,罗闸河二级水电站大坝拱肩开挖导致右岸高边坡出现局部滑坡事故和更大范围内的松动等诸多安全隐患,需治理。针对此类问题的共性及本边坡的特点,研究综合采用预应力锚索“锁脚”、土钉+挂网喷混凝土“护体”、内嵌软式排水管“降压”的方案对边坡进行加固。经日常巡视,以及对边坡位移、地下水位、锚索受力情况的监测,综合分析、验证了防渗处理的合理性、有效性,同时给出了管理维护的建议。该边坡于2014年治理完成,5 a来受6级以上地震影响3次,并经历2018年7.18暴雨,至今运行良好,对类似边坡的治理有一定的指导意义。

     

    Abstract: In 2013, the excavation of the arch abutment of dam of Luozha River II Hydropower Station caused many hidden safety hazards such as local landslide accidents and wider loosening of the high slope at the right bank, which needed to be treated.In view of the commonality of such problems and the characteristics of this slope, the scheme of "locking feet" by prestressed anchor cable, "protection" by soil nailing+hanging net sprayed concrete, and "pressure reduction" by built-in soft drainage pipe is used to reinforce the slope.After daily inspections and the monitoring of slope displacement, groundwater level and stresses on anchor cables, the comprehensive analysis and verification of the rationality and effectiveness of the antiseepage treatment are given, and the management and maintenance recommendations are also put forward.The slope treatment was completed in 2014.It had been affected by the earthquakes of magnitude 6 or above three times in the past five years, and experienced heavy rains on July 18, 2018.It has been running well so far, which has certain guiding significance for the treatment of similar slopes.

     

/