邢建营, 关志诚, 吕小龙. 面板堆石坝深覆盖层处理技术研究及在河口村水库工程中的应用[J]. 岩土工程学报, 2020, 42(7): 1368-1376. DOI: 10.11779/CJGE202007021
引用本文: 邢建营, 关志诚, 吕小龙. 面板堆石坝深覆盖层处理技术研究及在河口村水库工程中的应用[J]. 岩土工程学报, 2020, 42(7): 1368-1376. DOI: 10.11779/CJGE202007021
XING Jian-ying, GUAN Zhi-cheng, LÜ Xiao-long. Overburden treatment for concrete face rockfill dams and its application in Hekoucun project[J]. Chinese Journal of Geotechnical Engineering, 2020, 42(7): 1368-1376. DOI: 10.11779/CJGE202007021
Citation: XING Jian-ying, GUAN Zhi-cheng, LÜ Xiao-long. Overburden treatment for concrete face rockfill dams and its application in Hekoucun project[J]. Chinese Journal of Geotechnical Engineering, 2020, 42(7): 1368-1376. DOI: 10.11779/CJGE202007021

面板堆石坝深覆盖层处理技术研究及在河口村水库工程中的应用

Overburden treatment for concrete face rockfill dams and its application in Hekoucun project

  • 摘要: 深覆盖层上的面板堆石坝通常采用面板—趾板—连接板—防渗墙的防渗系统。由于连接板、趾板及坝体修筑在覆盖层上,填筑和蓄水期引起的覆盖层变形对防渗体接缝位移影响较大。因此,坝基覆盖层处理质量是保证工程安全的关键。针对坝基覆盖层处理问题,结合河口村水库工程,制定了固结灌浆、旋喷桩等多种坝基处理方案。采用非线性有限元法,系统研究了各坝基处理方案对坝体和防渗体接缝变形的影响。计算结果表明,对于固结灌浆和高压旋喷桩,两种方案均能满足设计要求。然而,固结灌浆方案实施困难,且效果不明显,很难达到预期的设计目标。最终选用高压旋喷桩方案,并提出了分区渐变式的新型布置形式。长期现场监测资料表明,加密区能有效降低防渗系统变形,处理后的覆盖层变形较小。

     

    Abstract: The concrete face, toe-slab, connecting slab, cut-off wall are usually used as the anti-seepage system of concrete face rockfill dams (CFRDs) on deep overburden. As the toe slab and dam body are built on the overburden, the deformation caused by filling and impoundment significantly affects the joint displacement of the anti-seepage system. Therefore, the quality of overburden treatment is the key to ensure the safety of the CFRDs. Aiming at the problem of overburden treatment, considering the Hekoucun project, several treatment schemes for dam foundation, such as dynamic compaction, consolidation grouting and high-pressure rotary spray, are proposed. Using the non-linear finite element method, the effects of various foundation treatment schemes on the joint deformation of anti-seepage system are systematically studied. The results show that consolidation grouting and high-pressure jet grouting pile can meet the design requirements. However, the consolidation grouting scheme is difficult to implement and difficult to achieve the design goal. Finally, the high-pressure jet grouting pile scheme is employed, and a new type of partition gradient layout is proposed. The on-site monitoring results show that the infiltration zone can effectively reduce the deformation of anti-seepage system. After reinforcement, the deformation of the overburden decreases significantly.

     

/